Tsundzukani Daycare Centre Kitchen Upgrade Project South Africa Technical report, 30th January 20223/2/2022 The Kitchen Upgrade project began in December 2021 at the Tsundzukani Bright Eye's Daycare Center, during the great rains of this season. With much joy and enthusiasm, our team met at Cashbuild, the local materials supplier in the Acornoek community. We selected and ordered the main building materials and equipment needed for our work, which were delivered the same day. The firm's manager thanked Plenty Canada for the ongoing support the organization has provided to the Tsundzukani Daycare for several years.
The original Center's kitchen facilities were very rudimentary as one can see from the images accompanying this report. Therefore, our project was based on an upgrade of the entire building structure into a more adequate standard to provide a healthy and safe environment for large scale meal preparation. The first construction step of the kitchen upgrade was to increase the size of the building structure. The next step was to install the roof trusses and continue with the exterior wall plastering, but the next big rain falls interrupted our work for a week or so. We were all happy for the rain anyway so it was a blessing in disguise. Our work continued in the next couple of days with the sun shining and the builders being able to complete the plastering of the exterior walls and install the new galvanized roof sheets just in time before the next downpour took place. Now that the roof was up the builders were able to plaster the interior walls and begin to install the wooden structure to support the ceiling which was successfully completed. The cornices were also placed and the first coat of paint was applied. The large window was additionally installed so to bring more light and fresh air into the kitchen environment, with a view to the Center's vegetable garden. As per our project plan, it is proposed to install an extra rain catchment and storage system in order to provide a separate running water supply to the kitchen facilities. This improvement will make the meal preparations and clean up easier and more sanitary, as currently there is no direct running water line into the building. Our building work is almost complete and if the weather permits it will take a couple of weeks to finish it up. The construction of two concrete tables around the interior walls will be added to the kitchen sink table. The kitchen floor will be painted with stoep paint to make it easier to sweep and mop. A second coat of paint will also be applied to the interior walls and ceiling. Other minor finishing jobs will be also accomplished. — Mwana Bermudes
0 Comments
Your comment will be posted after it is approved.
Leave a Reply. |
|